This Sunrise Wind project is a major milestone in the renewable energy industry. Situated offshore, approximately 30 miles east of Montauk, New York, this wind farm has a remarkable capacity of 924 megawatts. Ørsted Eversource commits to 924MW sunrise wind project whose establishment was approved after the United States Department of the Interior. It took place through the Bureau of Ocean Energy Management, presented a positive Record of Decision.
After careful consideration, Ørsted A/S and Eversource Energy, the project’s proponents, made the important Final Investment Decision. They expect the project’s Construction and Operations Plan to be authorized during the upcoming summer season.
The recent decision by the State of New York to negotiate a 25-year electricity supply contract from Sunrise Wind after successful discussions is a positive development for the project. In order for Ørsted A/S to move forward with acquiring Eversource’s 50% share and consolidating ownership, several other prerequisites must be fulfilled.
Eversource will continue to manage the onshore construction aspects of the Sunrise Wind project, showcasing a strong spirit of collaboration.
Its operational date is set for 2026, and Sunrise Wind is poised to make a significant impact on Suffolk County. Around 700 million US dollars associate with this project. This initiative has the potential to directly create 800 job opportunities.
Ørsted Eversource commits to 924MW Sunrise Wind project that will have a significant economic impact by creating numerous indirect jobs across New York State.
Key Points:
- Location: Approximately 30 miles east of Montauk, NY
- Capacity: 924 MW
- Investment: $700 million in Suffolk County
- Job Creation: 800 direct jobs, thousands of indirect jobs
- Operational Date: Expected in 2026
- Current Phase: Awaiting Construction and Operations Plan approval
Source: Sunrise Wind receives federal record of decision, takes final investment decision